Working in occupied premises

Fitting a full decorating job into weekends only

Office desks pushed together and covered in sheeting ready for a Saturday morning start

Two days a week sounds generous until you subtract setup, drying time and the pack-down needed before Monday's first arrival. A weekend-only programme has to be planned in whole weekends, not divided evenly across a job's total square metreage.

Why the maths isn't just half the week

A five-day job doesn't become a ten-weekend job by simple division. Every Friday setup and every Sunday pack-away eats into productive hours that a continuous week doesn't lose. We build the programme around what genuinely dries, cures and can be safely left between Sunday evening and the following Saturday morning.

Choosing where Friday afternoon starts

We usually arrive Friday afternoon to move furniture, mask and lay protection, so Saturday morning starts with a brush already loaded rather than another hour of preparation. This single decision often recovers close to a full day of coating time across a multi-weekend programme.

  • Protection and masking done Friday, before the site empties
  • First coats applied Saturday morning while cure time is longest
  • Second coats and detail work held for Sunday, finishing before pack-down

What has to be fully reinstated by Monday

Fire doors, signage, switches and any area used by staff or visitors first thing Monday must be back in normal use, not half-taped. We keep a standing checklist for each site of exactly what needs full reinstatement versus what can stay under protective sheeting for another week.

Carrying a wet edge across a gap of five days

Leaving a wall half-coated over a working week risks a visible line where old and new paint meet differently once dust has settled on it. We plan cut-off points at natural breaks — a corner, a doorframe, a full elevation — rather than stopping mid-wall because the clock ran out.

  • Work sequenced to finish whole rooms or whole walls, not partial sections
  • Colour batches recorded so a second weekend matches the first exactly

Questions we are asked about this

How many weekends will a typical office floor take?

It depends on the floor area and how much furniture needs moving, but we always give a weekend count up front rather than an ambiguous total, so you can plan staff access around it.

Can you guarantee the building is fully usable every Monday?

Yes — full reinstatement of fire routes, signage and working areas by Monday morning is a fixed requirement we build into the programme, not an aspiration.

What happens if weather or an emergency cancels a weekend?

We agree a contingency weekend in advance for exactly this reason, so one lost slot doesn't push the whole programme back by a month.

Reinstated fire exit signage and clear corridor ready for Monday morning arrivals

Tell us your available weekends and we'll return a room-by-room weekend sequence.

A weekend-only programme succeeds by planning in complete rooms, not equal hours.