Fit-out and refurbishment

Deciding whether flooring or decorating goes first

There is no single right order, and the answer changes with the type of floor going down. What matters is deciding deliberately, protecting the finish that goes in first, and not defaulting to whichever trade shouted loudest for the slot.

Correx floor protection sheeting taped down ahead of decorating work

The case for decorating first

Painting walls and ceilings before flooring means paint can run right down to the subfloor without worrying about splash or drips on an expensive finished surface, and any scaffold or step ladders can stand directly on a protected subfloor rather than a vulnerable new floor.

Skirting board left with a small scribe gap above an unfinished subfloor

The case for flooring first

Where flooring dictates a skirting height, or where a floor finish needs its own settling or acclimatisation period, it can make sense to lay it first and scribe skirtings to it afterwards. Carpet tiles and resin floors in particular are often better installed before final decoration so any residual dust and adhesive odour has cleared.

  • Resin and epoxy floors often need to fully cure before furniture or ladders go on them
  • Timber and LVT floors may need an acclimatisation period before scribing skirtings
  • Carpet tile adhesive fumes are better dissipated before final coats

Protecting whichever goes down first

Whichever order is chosen, the finish laid first needs continuous protection — correx or board on new flooring, dust sheets and edge protection on new paintwork — for the whole remaining programme, not just the day it's installed. Protection removed too early is the single biggest cause of late-stage damage.

How we work on this

  • We agree the flooring-versus-decorating sequence with the client before pricing rather than assuming.
  • We supply and fit floor protection that stays down for the length of the remaining programme.
  • We scribe skirtings to a confirmed floor level rather than guessing a height early.

Questions we are asked about this

Does it matter for a small office fit-out?

It matters less on a small single-room job, but on multi-room fit-outs the sequence affects protection cost and rework risk enough to plan properly.

Can skirtings be fitted before the floor is down?

Yes, with a small gap left to scribe to the final floor height, which is often tidier than trying to cut flooring precisely to a fixed skirting.

What protection do you use on new floors?

Correx or hardboard on hard floors, and breathable protective film on carpet and carpet tile, taped at joints rather than left loose.

Tell us your flooring type and installation date and we will recommend a sequence for your job.

The right order depends on the flooring type, but whatever goes down first needs protecting until the last trade leaves.

Start your project

Planning a commercial painting or decorating project?

Speak to a Hampshire commercial decorating contractor that turns up, communicates clearly and delivers a finish that lasts.